This guide is intended to guide you through the process of performing a White Glove Inspection. To help you perform the inspection in an orderly process, we have divided the WGI into 12 sections, each corresponding to specific areas of a Beverly Hills Rejuvenation Center facility.
In order to provide you with a strategic plan to not only inspect each section, but also assign responsibility to fix any issues found in each section, we have broken down those sections into Element's. Those elements are:
To view the Exterior specifications used in the build-out process a BHRC location, click here.
* If there are any items that are non-compliant, detail what is wrong, what the solution is, and the cost in the "Notes" field for this section. Total the costs and put those costs in the "Cost To Fix" field.
To view the Lobby specifications used in the build-out process a BHRC location, click here.
* If there are any items that are non-compliant, detail what is wrong, what the solution is, and the cost in the "Notes" field for this section. Total the costs and put those costs in the "Cost To Fix" field.
The Front Desk is part of the Lobby, to view the specifications used in the build-out process a BHRC location, click here.
* If there are any items that are non-compliant, detail what is wrong, what the solution is, and the cost in the "Notes" field for this section. Total the costs and put those costs in the "Cost To Fix" field.
To view the Inventory Closet specifications used in the build-out process a BHRC location, click here.
* If there are any items that are non-compliant, detail what is wrong, what the solution is, and the cost in the "Notes" field for this section. Total the costs and put those costs in the "Cost To Fix" field.
To view the Nurses Station specifications used in the build-out process a BHRC location, click here.
* If there are any items that are non-compliant, detail what is wrong, what the solution is, and the cost in the "Notes" field for this section. Total the costs and put those costs in the "Cost To Fix" field.
To view the Consultation Room specifications used in the build-out process a BHRC location, click here.
* If there are any items that are non-compliant, detail what is wrong, what the solution is, and the cost in the "Notes" field for this section. Total the costs and put those costs in the "Cost To Fix" field.
To view the Treatment Room(s) specifications used in the build-out process a BHRC location, click here.
* If there are any items that are non-compliant, detail what is wrong, what the solution is, and the cost in the "Notes" field for this section. Total the costs and put those costs in the "Cost To Fix" field.
To view the Manager's Office specifications used in the build-out process a BHRC location, click here.
* If there are any items that are non-compliant, detail what is wrong, what the solution is, and the cost in the "Notes" field for this section. Total the costs and put those costs in the "Cost To Fix" field.
To view the Manager's Office specifications used in the build-out process a BHRC location, click here.
* If there are any items that are non-compliant, detail what is wrong, what the solution is, and the cost in the "Notes" field for this section. Total the costs and put those costs in the "Cost To Fix" field.
To view the Manager's Office specifications used in the build-out process a BHRC location, click here.
* If there are any items that are non-compliant, detail what is wrong, what the solution is, and the cost in the "Notes" field for this section. Total the costs and put those costs in the "Cost To Fix" field.
To view the Manager's Office specifications used in the build-out process a BHRC location, click here.
* If there are any items that are non-compliant, detail what is wrong, what the solution is, and the cost in the "Notes" field for this section. Total the costs and put those costs in the "Cost To Fix" field.
To view the Manager's Office specifications used in the build-out process a BHRC location, click here.
* If there are any items that are non-compliant, detail what is wrong, what the solution is, and the cost in the "Notes" field for this section. Total the costs and put those costs in the "Cost To Fix" field.
To view the Manager's Office specifications used in the build-out process a BHRC location, click here.
* If there are any items that are non-compliant, detail what is wrong, what the solution is, and the cost in the "Notes" field for this section. Total the costs and put those costs in the "Cost To Fix" field.